Early Dates
The soonest possible date a task can start or finish
These values are calculated based on durations and dependencies between all tasks in a project.
As soon as possible
Legacy CPM set's nominal dates to equal early dates. This means it wants you to start everything as soon as logically possible, with no regard to resource constraints.
This severely limits the flexibility of your schedule. What most people do to account for this is create logic that shouldn't exist.
For example, they'll put a "Final Paint" task to succeed another "Final Paint" task, not because one can't start until the other is finished, but because there's only one paint crew and they can only work on one area at a time. The flaw here is the initial plan had Area 1 painted before Area 2 but, since its construction things happen, and Area 2 might eventually be ready first, this typically goes unnoticed until its too late.
Early Start
early_start
The earliest a task can start is based on when its dependencies are finished or started, depending on the dependency type.
Early Finish
early_finish
The earliest a task can finish is based on its early_start
and duration.
Milestones
Unlike Tasks, Milestones have a single early_date
field. This is the soonest a Milestone can occur.
Legacy CPM
In LeanCPM, there are no “Planned Dates” or “Original Dates“ .